Due to the increase in quantity of water accepted by Dayou Town Sewage Plant in Xiangshui County, it is needed to carry out extension on a sewage treatment facility in the original plant area. This project adopts the parallel connection of 5 mobile systems of RPIR to build a set of sewage treatment facility, with the treatment capacity machine per machine of 200m³/d and total treatment capacity of 1000m³/d, and the effluent follows the first grade A standard of the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB18918-2002).
Project Highlights:
1. Mobile system of RPIR is used for combined treatment, and the construction period is short, taking only 7 days from the equipment mobilization to supplying water and reaching the standard;
2. The mobile system of RPIR is highly intensive, which shortens the process flow and saves the floor area.